Jacksonville International Airport is installing access control, security and a public address system at a project cost of $8 million.
Behind-the-scenes tour shows progress on new Jacksonville airport concourse featuring "smart glass" technology and more space than other concourses.
The Jacksonville Aviation Authority provided a glimpse into the new Concourse B that is currently under construction at the Jacksonville International Airport.
VanLoh is particularly relieved they haven't hit any turbulence - the project is on schedule and on budget for $340 million ...
SALT LAKE CITY — Salt Lake City International Airport held a grand opening for its Concourse B Tuesday morning. "Concourse B opened this morning with a total of 21 gates to house Alaska, American, ...
JACKSONVILLE, Fla. — We’re getting a closer look at a project underway at Jacksonville International Airport to add a new concourse and additional security checkpoint gates, which would make flying in ...
Concourse B at Jacksonville International Airport is under construction and scheduled to open by the end of December. Jacksonville International Airport’s Concourse B is 10 months out from adding six ...
Having the foresight to approve orders for materials early was one key to keeping the project on time and under budget, JAA ...
Hartsfield-Jackson International Airport has completed repairs on a water main break on Concourse B, more than two days after the leak caused the closure of some concessions and restrooms on the ...